Background
A consortium of eight Australian and International resources companies, Wiggins Island Coal Export Terminal Pty Ltd (WICET) operates a recently opened coal-loading terminal in Gladstone, Queensland. This terminal was built due to the increasing coal storage and ship-loading demands on the region, plus the fact that the existing Gladstone facility was nearing its capacity. WICET enables an additional 27 million tonnes of coal to be exported from the Port of Gladstone each year, with the capability to export up to 120 million tonnes per annum when fully developed.
The Challenge
WICET required a turnkey technology solution for the new terminal – one that delivered a highly available network, as well as robust and scalable ICT infrastructure to support critical applications. The main challenge was ensuring there was no disruption across various construction contractors and zones, with zero downtime or interference to the construction critical path. Data#3 was chosen to implement the solution for the following reasons:
The Solution
Data#3 proposed an end-to-end technology solution that included a site-wide communications network (wired and wireless), state-of-the-art information systems platforms, and supporting infrastructure for manufacturing and process control environments. The solution used the following technology:
In order to minimise onsite disruption and ensure project milestones were met, the solution was delivered in the following stages:
The Outcome
WICET now benefits from a highly available network, plus a robust and scalable ICT platform that leverages world-leading Cisco and associated vendor capabilities. The project was completed on time and under contracted budget, with zero disruption to the construction critical path. Data#3’s offsite warehouse, configuration and integration facilities for staging and factory acceptance testing meant the risk of technical failure during commissioning was reduced. Both Data#3 and WICET were then able to utilise the network pre-completion to test and commission operational systems for Information Management, Process Control and Manufacturing Execution.
Data#3 achieved zero related Work Health Safety, quality and technical defect notices over the 30-month engagement. The network was commissioned and handed over in one week, with onsite training, documentation and early life support provided during the go-live period.
Additionally, Data#3 negotiated and project managed multiple suppliers and specialist sub-contractors in a construction context, without construction disruption.
“The Data#3 Project Team delivered the outcome WICET Engineers had planned. They became a valuable extension of both our project and operational teams. This enabled us to focus on delivering critical applications,” says Rob Davies, Area Manager, WICET.
“Data#3’s deliverables were of outstanding quality and their documentation and quality set a benchmark for the project.”
Tags: Cisco, Cisco Unified Communications, Cloud, HP, Microsoft, VMware